In late July 2024, the "Source-Grid-Load-Storage Integration" pilot project was launched in Luofu Town, Nandan County, where photovoltaic facilities and 220KV confluence stations were built. The project construction land involves 149 plots of land in 6 administrative villages in the town, totaling 6,798 mu. Since the project was launched, the Standing Committee of the People's Congress of Luofu Town has closely followed the decision-making and deployment of the Party Committee and the government, and has made supporting project construction a priority in the performance of the People's Congress's duties. It has actively played the role of representatives, taken the initiative, provided front-line services, and fully cooperated with the construction unit to do a good job in mass ideological mobilization, land surveying and mapping, and other work, providing strong guarantees for the orderly advancement of the project.
Explain policies, resolve doubts, and deliver the "good voice" of project construction
In the process of advancing the work, some people lack scientific knowledge of the photovoltaic industry and have many concerns about the development of photovoltaic projects, which has led to slow progress in the land transfer work in some villages and groups. To this end, the presidium of the town's People's Congress gave full play to the role of grassroots people's congress representatives and formed 6 "project mobilization" teams to go deep into the villages and towns to explain the significance of project construction, the standards for compensation for young crops, the accuracy of physical surveys, and the calculation of transfer accounts, so that the masses can take a "reassurance pill". "The key to doing a good job in the land transfer of photovoltaic projects is to respect the wishes of the masses. Even if the masses have misunderstandings, they must do their work carefully, patiently, and warmly." Chen Hongyang, a representative of the People's Congress of Luofu Town, introduced. It was the people's congress representatives and staff who explained the reason and moved the emotions, patiently and meticulously did the ideological work of the masses, softened the "hard knot" in the hearts of the masses, and the attitude of the masses changed from non-cooperation to active response.
Investigate public sentiment, accept public opinion, and build a "bridge of public opinion" for communication and coordination
The photovoltaic project has a wide range of land use, tight time and complex situations, involving the vital interests of the people and enterprises involved in the land acquisition and leasing, which is the most difficult "hard bone" to chew in the process of project promotion. The presidium of the town people's congress explored the establishment of a "mobile NPC representative contact point" to extend the window for representatives to contact the masses to the fields and farmers' homes. In response to the many demands of the masses on land rental income, young crop compensation standards and other aspects, the representatives strengthened the "two-way" contact with the project units and the masses. On the one hand, from the perspective of the masses, they collected the "problem list" of the masses and helped the masses calculate the "economic account"; on the other hand, they strengthened communication and coordination with enterprises, focused on solving the reasonable demands of the masses, and built a "bridge of communication" between the masses and the government and enterprises. The NPC representatives involved in the land lease red line also gave full play to the "head goose effect", starting from their own homes, taking the lead in cooperating in land demarcation and surveying and mapping work to dispel the ideological concerns of the masses. Up to now, the town has completed the surveying and mapping of 2,800 acres of land acquisition and leasing.
Focus on supervision, strengthen services, and deepen the "responsibility field" of project supervision
The Standing Committee of the People's Congress of Luofu Town regularly organizes people's congress representatives to follow up on service projects, actively build bridges between project units and the masses, organize people's congress representatives to go deep into the land acquisition and surveying site, inspect the progress of project construction 6 times, and fully understand the progress and existing problems of land acquisition and surveying. It promptly reported 8 demands raised by the masses to the owner unit, put forward 12 targeted opinions and suggestions, coordinated to solve 8 problems, supervised the progress of the project throughout the process, tracked and evaluated the results, and ensured that the project was smoothly promoted according to the planned time nodes.
"In the next step, we will continue to do a good job in land transfer. For the land that has been measured, we will organize the signing of contracts as soon as possible to ensure the smooth start of the project." said Pan Zhihua, deputy to the Nandan County People's Congress and secretary of the Luofu Town Party Committee. (Liang Chunyi, Pang Jian, Du Ruiyuan)
Previous article:Hundreds of commercial buildings form a virtual power plant, electric vehicles "transport" electricity to earn profits
Next article:Anhui has introduced a series of measures to promote the development of advanced photovoltaic and new energy storage industries
- Popular Resources
- Popular amplifiers
- Increase the proportion of capacity leasing! Ningxia issued a notice on promoting the healthy development of energy storage
- A brief discussion on the application of energy storage power stations in cement plants
- Indian Army uses hydrogen microgrid to supply electricity in Himalayas
- CATL's Xiaoyao super hybrid battery fully opens the era of hybrid "large capacity"
- Gansu's new energy storage installed capacity exceeds 4 million kilowatts
- Hebei Weixian 100MW/400MWh energy storage power station project with a total investment of 650 million yuan started
- The world's first pioneering technology! Chengdu East New District's first 10 billion-level leading project is fully operational
- Shandong publishes registration information of two virtual power plants, capable of regulating 14.625 MW of electricity
- Musk: Tesla's energy storage business 'growing like wildfire'
- LED chemical incompatibility test to see which chemicals LEDs can be used with
- Application of ARM9 hardware coprocessor on WinCE embedded motherboard
- What are the key points for selecting rotor flowmeter?
- LM317 high power charger circuit
- A brief analysis of Embest's application and development of embedded medical devices
- Single-phase RC protection circuit
- stm32 PVD programmable voltage monitor
- Introduction and measurement of edge trigger and level trigger of 51 single chip microcomputer
- Improved design of Linux system software shell protection technology
- What to do if the ABB robot protection device stops
- CGD and Qorvo to jointly revolutionize motor control solutions
- CGD and Qorvo to jointly revolutionize motor control solutions
- Keysight Technologies FieldFox handheld analyzer with VDI spread spectrum module to achieve millimeter wave analysis function
- Infineon's PASCO2V15 XENSIV PAS CO2 5V Sensor Now Available at Mouser for Accurate CO2 Level Measurement
- Advanced gameplay, Harting takes your PCB board connection to a new level!
- Advanced gameplay, Harting takes your PCB board connection to a new level!
- A new chapter in Great Wall Motors R&D: solid-state battery technology leads the future
- Naxin Micro provides full-scenario GaN driver IC solutions
- Interpreting Huawei’s new solid-state battery patent, will it challenge CATL in 2030?
- Are pure electric/plug-in hybrid vehicles going crazy? A Chinese company has launched the world's first -40℃ dischargeable hybrid battery that is not afraid of cold
- Come to Infineon flagship store to find good things in autumn! Get coupons and win a 50-yuan JD card
- [2022 Digi-Key Innovation Design Competition] Material unboxing ESP32-S3 SHT30 LMG5200 and other devices
- Help, power circuit analysis
- If there is a bug in the third-party code, how can everyone adapt it to the original version after it is fixed?
- Share a general good book Digital Signal Processing C Language Program Collection-DSP Algorithm Encyclopedia C Language Version Original Book
- This article explains what parameters and indicators should be measured when designing a switching power supply.
- ATMEL SAM3N2C chip timing is inaccurate
- TMS320C6000 Image Library (IMGLIB)
- I'm just learning about MEMS. Does anyone know what the problem is with the unicleo GUI not being able to recognize the MEMS expansion board?
- MSP430 system clock ACLK, MCLK, SMCLK