China National Nuclear Corporation's first large-scale grid-side shared energy storage project was successfully connected to the grid

Publisher:温雅如风Latest update time:2022-12-08 Source: 中核汇能Author: Lemontree Reading articles on mobile phones Scan QR code
Read articles on your mobile phone anytime, anywhere

On December 7, the CNNC Tongxinquanyan 100MW/200MWh energy storage power station was successfully connected to the grid, marking the official entry of CNNC's first large-scale grid-side shared energy storage project into production and operation. This is the first large-scale grid-side shared energy storage project in Ningxia, and also the first such energy storage project to be connected to the grid in Ningxia.

The project started on June 1, 2022. It is a key project of Ningxia's "Six Hundreds" in 2022. It is located in Weizhou Town, Tongxin County, Ningxia, with a total investment of about 400 million yuan. A total of 30 sets of 3.45MW/6.7MWh energy storage systems will be built. The battery uses lithium iron phosphate batteries with an average annual discharge of 50 million kWh. The project will serve as a "power bank" on the grid side, improve the flexible adjustment ability of the grid, effectively realize the peak load reduction and valley filling of the grid, alleviate the peak power supply pressure, and promote the consumption of new energy. It is of great significance to accelerate the application of large-scale energy storage in Ningxia in power peak load regulation and renewable energy power grid connection.

Reference address:China National Nuclear Corporation's first large-scale grid-side shared energy storage project was successfully connected to the grid

Previous article:The explosion of new energy vehicles has increased the price of lithium ore by 10 times. Ningde, Yichun and other cities have proposed to build a "lithium capital"
Next article:Tongrun Equipment intends to "bet" on the photovoltaic energy storage track and has closed 11 daily limits

Latest New Energy Articles
Change More Related Popular Components

EEWorld
subscription
account

EEWorld
service
account

Automotive
development
circle

About Us Customer Service Contact Information Datasheet Sitemap LatestNews


Room 1530, 15th Floor, Building B, No.18 Zhongguancun Street, Haidian District, Beijing, Postal Code: 100190 China Telephone: 008610 8235 0740

Copyright © 2005-2024 EEWORLD.com.cn, Inc. All rights reserved 京ICP证060456号 京ICP备10001474号-1 电信业务审批[2006]字第258号函 京公网安备 11010802033920号