China Energy Storage Network News: In 2021, the State Grid put into operation 44,000 kilometers and 280 million kVA of 110 kV and above AC projects, completing 101.4% of the annual plan; 41,000 kilometers and 250 million kVA were started, completing 100.7% of the annual plan. The company put into operation 2,840 kilometers and 32 million kW of DC projects, and started 2,285 kilometers and 18 million kW. The investment in grid infrastructure was completed at 402.48 billion yuan, completing 100.5% of the annual plan.
2021 was a very difficult year for the company to complete its construction tasks. The epidemic spread in multiple places, and natural disasters such as floods occurred frequently, which put great pressure on completing the tasks. The company's infrastructure front thoroughly implemented the decisions and deployments of the company's party committee, actively promoted the implementation of the "one body and four wings" development layout, conscientiously implemented the work requirements such as carbon peak, carbon neutrality and new power system construction, faced up to difficulties, worked hard to overcome difficulties, and took multiple measures to fully promote the construction of the power grid, achieving a double excess in construction scale and investment scale, and successfully completed the annual construction tasks.
白鹤滩接网、川藏铁路供电一期工程提前建成,冬奥配套、边防供电二期工程圆满收官,中央部署重大战略性工程建设任务全面完成。雅中—南昌、陕北—武汉特高压直流,南昌—长沙等特高压交流工程建成投运,显著提升跨区跨省资源配置能力。湖南鲤鱼江电厂改接、永州电厂送出、北京东—通州、西藏拉萨调相机等电网加强工程全面建成,持续完善地区主网架水平。丰宁抽水蓄能电站,新疆库车—阿克苏—巴楚Ⅱ回、青海托素、四川杨房沟送出、西藏大古水电送出等工程按期投运,助力碳达峰、碳中和目标实现。煤改电、农网巩固提升、电铁配套、雄安新区配套等一大批关系国计民生的供电工程有序推进,积极服务国家民生改善和新发展格局。
The company holds infrastructure coordination meetings every month to closely track the construction of key projects and promptly coordinate and resolve difficult engineering issues. The relevant departments of the headquarters work together efficiently, promptly resolve key tasks such as pre-planning, material supply, and power outage arrangements in accordance with the key project construction plan, strengthen intra-provincial and inter-provincial coordination and assistance, and rationally allocate construction resources, effectively ensuring the smooth progress of key projects.
Previous article:The highest phase-shifting project in China successfully passed the 168-hour trial run
Next article:Building a new power system for 30 and 60 years: Thoughts on China Power 4.0
- Popular Resources
- Popular amplifiers
- Increase the proportion of capacity leasing! Ningxia issued a notice on promoting the healthy development of energy storage
- A brief discussion on the application of energy storage power stations in cement plants
- Indian Army uses hydrogen microgrid to supply electricity in Himalayas
- CATL's Xiaoyao super hybrid battery fully opens the era of hybrid "large capacity"
- Gansu's new energy storage installed capacity exceeds 4 million kilowatts
- Hebei Weixian 100MW/400MWh energy storage power station project with a total investment of 650 million yuan started
- The world's first pioneering technology! Chengdu East New District's first 10 billion-level leading project is fully operational
- Shandong publishes registration information of two virtual power plants, capable of regulating 14.625 MW of electricity
- Musk: Tesla's energy storage business 'growing like wildfire'
- Innolux's intelligent steer-by-wire solution makes cars smarter and safer
- 8051 MCU - Parity Check
- How to efficiently balance the sensitivity of tactile sensing interfaces
- What should I do if the servo motor shakes? What causes the servo motor to shake quickly?
- 【Brushless Motor】Analysis of three-phase BLDC motor and sharing of two popular development boards
- Midea Industrial Technology's subsidiaries Clou Electronics and Hekang New Energy jointly appeared at the Munich Battery Energy Storage Exhibition and Solar Energy Exhibition
- Guoxin Sichen | Application of ferroelectric memory PB85RS2MC in power battery management, with a capacity of 2M
- Analysis of common faults of frequency converter
- In a head-on competition with Qualcomm, what kind of cockpit products has Intel come up with?
- Dalian Rongke's all-vanadium liquid flow battery energy storage equipment industrialization project has entered the sprint stage before production
- Allegro MicroSystems Introduces Advanced Magnetic and Inductive Position Sensing Solutions at Electronica 2024
- Car key in the left hand, liveness detection radar in the right hand, UWB is imperative for cars!
- After a decade of rapid development, domestic CIS has entered the market
- Aegis Dagger Battery + Thor EM-i Super Hybrid, Geely New Energy has thrown out two "king bombs"
- A brief discussion on functional safety - fault, error, and failure
- In the smart car 2.0 cycle, these core industry chains are facing major opportunities!
- Rambus Launches Industry's First HBM 4 Controller IP: What Are the Technical Details Behind It?
- The United States and Japan are developing new batteries. CATL faces challenges? How should China's new energy battery industry respond?
- Murata launches high-precision 6-axis inertial sensor for automobiles
- Ford patents pre-charge alarm to help save costs and respond to emergencies
- 【NXP Rapid IoT Review】W4 Bluetooth Review
- Transistor problem
- 【AT-START-F425 Review】Using the USB flash drive file storage function to achieve data recording
- E103-W01-BF test version use
- Pingtouge Xuantie CPU debugging system
- Python Software Foundation Welcomes Google as First Top-Level Visionary Sponsor
- What do strong pull-up, strong pull-down, weak pull-up, and weak pull-down mean?
- 2019 TI Automotive Electronics Applications Seminar Highlights Video Review
- I decided to quit my job and develop my operating system full-time (transferred)
- Design rules for four-layer PCB